Shearwater Parkway Construction Entrance Closing Soon
ALERT CATEGORY: Walls & Gates   |   ALERT EXPIRES: January 22, 2021
The builder has informed the CDD that they intend to close off the Shearwater Parkway construction entrance soon. We do not have an exact date, but residents will need to resume using the two main entrances once the construction access is closed.

Should you have any questions, please contact the CDD District Manager at 407-841-5524.

 

ALERT PUBLISHED: 01/08/21 3:28 pm  |  Jason Showe   |   ALERT LAST MODIFIED: 01/08/21 3:28 pm  |  Jason Showe

District Updates

The purpose of this page is to show you recent updates about the community over the last 4 weeks. To look back further at a specific topic please select a category on the District Facilities Supervisor Reports page.

If you are looking for recent email communications that were sent, please visit the District Communications Archive.

If you are looking for the most recent documents posted, please visit the All Documents page.

If you are looking for additional information on upcoming, in progress or recently completed Capital Improvement Projects, please visit the Capital Improvement Projects page.

Clubhouse & Fitness Center

Report Clubhouse & Fitness Center Notes
12-18-20

The Clubhouse Chrirtmas decorations on the interior were put out, a special thanks goes out to the Wellmans and their volenteeres for putting out the tree and decorations throughout the Clubhouse. Redwire has been installing the FIRE SYSTEM troughout the Clubhouse this week and shoudd be complete early next week by Monday or Tuesday 12-21-20 or 12-22-20.

10-23-2020

Browns Fitness Services LLC came out and made the necessary repairs to the (KNEE PRESS MACHINE) at the Clubhouse fitness room. Evidently the cable connecter end had pulled off from the cable. The tech (Mike) refastened a new cable end fastener into place to cable as needed. He made the proper adjustments to this equipment for smoother operation.

10-16-2020

The Clubhouse is now outfitted with all new exterior lock assemblies with new interior crash bars. This scope of work was performed by CDA Solutions, in a professional workman type manner. The leg press machine in the Clubhouse fitness room is (OUT of ORDER) at this time and the tech was notified. This machine will be repaired on Monday October 19,2020

10-02-2020

CDA Solutions (locksmith company) has installed 3 new lock assemblies with crash bars on the Clubhouse rear exterior doors. There is only one exterior lock assembly to install with crash bar (CLUBHOUSE MAIN FRONT DOOR) remaining, and all 12 of the exterior lock assemblies with crash bars have been installed. The Clubhouse main front door is going to need a longer crash bar because this door is wider than the other doors . The necessary hardware has been ordered and will be installed when the parts come in on order. All of the EMERGENCY LIGHTING fixtures were tested and all of them are functioning properly as of 10/01/20.

View All Clubhouse & Fitness Reports

Pool & Pool Deck

Report Pool & Pool Deck Notes
12-18-20

The pool tech from Brevard Pools has been monitoring our swimming pool chemicals and remains on a 3 times per week schedule. He reported to me that each time he visits our Community pool he has to add 10 gallons of Chlorine and one 2pound scoop of stabilizer, or stabilizer when necessary. For instance today 12-18-20 he added the 10 gallons of chlorine and no stabilizer, because the pool chemestry did not need it. He also turned the auto fill back on, because it had been off for some time as I monitored the pools water level. The regular water evaporation was taking place so the auto fill was turned back on. We will continue monitoring the pools chemestry and we will add chemicals as needed.

10-23-2020

We are continuing monitoring the chemical and water levels in the swimming pool. We are also continuing the 3 times per week services by Brevard Pools LLC until further notice while we gather / monitor information

10-16-2020

We are continuing to monitor the chemical and the water levels of the pool, We have been experiencing the chlorine levels dropping off, we've been adding a bit more stabilizer to help in our efforts / ability to keep the chemicals (CHLORINE) levels normal .I've been testing these levels daily and in constant communication with our pool tech (Daniel) of Brevard pools. Normally this time of year the pool tech only visits us twice a week .Due to this chemical imbalance situation I've had the pool tech remaining his visits to 3 times a week. until further notice.

10-02-2020

The pool has been having issues of holding the chlorine levels, a dye test was performed on September 22,2020 to check the pool for leaks of any kind. There seems to be a suspect of a leak in the pool display fountains. These were shut off to determine if there could be water loss from this issue, we also turned off the auto fill to be able to determine if in deed there was any water loss other than normal evaporation. By process of elimination we were trying to monitor any drastic water loss in the pool. The stabilizer levels were a bit low, so stabilizer was added to boost the stabilizer levels. This will allow the chlorine levels to hold longer. The black algae spots are still present but not as prevalent. We will continue to monitor the pool chemical levels daily and we will need to investigate and test the display fountains plumbing probably next month or when the pool swimming traffic slows down somewhat. A new auto fill was installed because the old one had a small leak in the housing itself.

View All Pool & Pool Deck Reports

Irrigation

Report Irrigation Notes
12-18-20

The irrigation controler for PS#1 was not functioning properly and I was not able to remotely control any zones with my cell phone. I reported this to Tuyler Salads of Insite irrigation and he concluded that tjhe temporary repair that was made to this controler antena was indeed failing. The issues must have been repaired because he contacted me and now miraculously I have my remote control abilities back functioning once again Thank you Tyler Salas for the repairs to the irrigation system now allows me to be able to keep water in the South Patrick entrance fountain. Fountain now working.

10-23-2020

The mainline break that was behind 710 Montecito Drive has been repaired properly. once the repair had cured 24 hours the system was put back into service. A complete inspection of the repair was made before backfilling the 6" mainline repair. All is well now, PS#2 is back in service and back on the watering schedule. Addressed work orders

Installed sprinklers on new plants pump station 1

Started wet check on pump station 1 and found the wiring issues after zone 9

Repaired wiring issues found while wet checking

10-16-2020

We have had issues with PS#2, the metal clamps that hold the filters assemblies in tact fell victim to the elements causing the filter covers to separate (FAIL) and cause a leak and the low pressure alarm from massive flow sensors to cause the system to shut down. Hoover came out this week 10-13-20 and make the necessary repairs to the filter manifold. We then had a leak occur in the 6"main line in the proximity behind 710 Ventura Drive. This leak was located and repaired ASAP Unfortunately the cure time on such a mainline break is 24 hours. While the PS#2 pump station was not functioning a water truck was brought in by Paradise Lawn & Irrigation to water all of the areas of concern that PS#2 normally waters.

10-02-2020

There are two zones not functioning from the clock. Zone 2 on the East clock and zone 18 on the West clock.
We are continuing to water new sod twice daily and established sod 3x a week. Let us know if there are any questions or concerns.
Wet check clock D

Repairs found during clock D wet check

addressed work orders

View All Irrigation Reports

Landscaping & Lighting

Report Landscaping & Lighting Notes
12-18-20

A extra flair for the Community street lights The HOA had a company come in and install Christmas Reefs on the near 50 steet lights in the Community This looks simply amazing Thanks goes out to the HOA! for your Community Christmas enhansment project.

10-23-2020

The 3 street lights that were (OUT of ORDER) on Montecito Drive, Simeon Drive, and Carlsbad Drive were repaired by Gault Electric LLC on 10/22/20. After trouble shooting the series of street lights starting on Carlsbad Drive, a conduit was found separated from the builder (Vintage Homes) construction work area knocking out the power that feeds the series of street lights that continue following around Montecito Drive and Simeon Drive street light poles / fixtures. Gault made the necessary repairs to conduits, once completed with the conduit repairs; all new wiring was pulled through the conduits to each and every street light poles and fixtures from Carlsbad Drive, Montecito Drive, and to Simeon Drive. This conduit repair and the pulling of new wire to the street lights is the responsibility of the builder (VINTAGE HOMES). All street lights are functioning fine now at this time. An independent street light was not working on 735 Simeon Drive area,. It turned out to be a bad street light bulb. A new bulb was installed and that street light is working fine now at this time.

10-16-2020

It was reported that there are street lights not functioning in the new section on Simeon Drive. I came into the Community last evening to do a drive by 10-16-20 to determine which street lights and how many actual street lights were actually not functioning. I report that there are 4 street lights (OUT of ORDER) in the area Montecito Drive & Simeon Drive intersection near the Montecito mailboxes. There is also a few on the Simeon Drive strip between Montecito Drive and Clemente Drive. I had contacted Gault Electric LLC of these street lights outage and they'll be out in the later part of next week to make the repairs

10-02-2020

Nothing to report at this time.

View All Landscaping & Lighting Reports

Lakes

Report Lake Notes
12-18-20

The TDS levels were taken and recorded for the Month of December. The TDS meter went bad, it was under warrenty so we were able to simply exchange it. we used the back up meter (OLD one) for Decembers readings.

10-23-2020

Nothing to report at this time.

10-16-2020

Nothing to report at this time.

10-02-2020

The TDS levels were taken & recorded on 10/01/20. The lakes were treated for overgrowth of vegetation (hydrilla) from all 6 of the lakes on Treatment done by Amercan EcoSystems Inc. on September 29,2020

View All Lake Reports

Lake Fountains

Report Lake Fountains Notes
12-18-20

All of the fountains are opperating fine at this time

10-23-2020

All 6 lake fountains are working fine at this time. all 4 entrance and exit fountains are also working fine at this time

10-16-2020

All 6 lake fountains are functioning fine at this time and the lights are working fine also. The fountain lights will need to be re-adjusted whenever we have the time change. Both entrance & exit fountains at the Shearwater Parkway were drained and though rally cleaned of scaling and staining build up. The other two entrance & exit fountains off of South Patrick will be though rally cleaned next week This scope of work has been done by Randy McGrath (DFS).

10-02-2020

All 6 lake fountains are operational at this time and the lighting was adjusted to daylight hours. This will be revisited and readjusted to the up-coming time change.

View All Lake Fountain Reports

Gates & Walls

Report Gates & Walls Notes
12-18-20

I installed lighted Christmas decorations on all of the entrance and exit Community Gates for the Christmas holidays for brightening up accent Merry Christmas Holiday

10-23-2020

FDC came out on 10/21/20 and performed preventative maintenance on all entrances and exits gate operators.

10-16-2020

Nothing to report at this time.

10-02-2020

2 pedestrian gates were removed by the crew at GMS to be taken and refurbished / repairs. Once the necessary repairs are made they will be put back into service. The location of these gates are as follows:(1) The exit pedestrian gate Shearwater parkway by round about. (2) The most Eastern pedestrian gate on Shearwater Parkway

View All Gate & Wall Reports

Streets & Sidewalks

Report Streets & Sidewalks Notes
12-18-20

Nothing to report at this time.

10-23-2020

Nothing to report at this time.

10-16-2020

Nothing to report at this time.

10-02-2020

Nothing to report at this time.

View All Street & Sidewalk Reports

Playground

Report Playground Notes
12-18-20

The replacement parts for playground equipment has been ordered and we await the arrival sometime soon perhaps late January or early February for the arrival.

10-23-2020

Nothing to report at this time.

10-16-2020

Nothing to report at this time.

10-02-2020

Nothing to report at this time.

View All Playground Reports

Other Areas

Report Other Notes
12-18-20

Nothing to report at this time.

10-23-2020

Nothing to report at this time.

10-16-2020

Nothing to report at this time.

10-02-2020

All 4 bike racks were treated and cleaned up with stainless steel cleaner / polish as needed.

View All Other Note Reports

Last 5 Updated Documents

Last Updated

File Date
1.District Staff Directory12-29-2020 16:12 pm
2.Job Application Form12-17-2020 16:02 pm
3.October 2020 Invoices12-02-2020 12:13 pm
4.December 2020 Meeting Agenda11-26-2020 5:22 am
5.2018-2023 CIP Project Plan11-19-2020 13:37 pm