CLUBHOUSE & GYM

Nothing to report at this time.

POOL & POOL DECK AREA
IRRRIGATION

· We completed all of the approved repairs from Septembers irrigation inspect

· The October irrigation inspection was completed and we will be sending that report over soon

· We have received a pre-approval to make CDD repairs while we are onsite completing our inspection.

· We repaired a mainline outside of the wall along Shearwater.

· We installed 2 spigots were installed along Shearwater.

· Both pump stations and all 4 controllers were inspected.

LANDSCAPING & LIGHTING

Nothing to report at this time.

PONDS

The ponds are extremely low, and we are in much need for rainfall. We are only using one Artisan well from pond #2at this time to help supplement our water shortage. We recently did our pond samples and the readings show a slight elevation in the (Total Dissolved Solids). We are within the levels allowing us to irrigate with our pond waters at this time.

POND FOUNTAINS

All 6 fountains time clocks and lighting clocks were adjusted accordingly to the new time change

STREETS & SIDEWALKS

Nothing to report at this time.

GATES & WALLS

There is a meeting on 11-14-2018 Where the interior and exterior color schemes will be discussed and voted upon. At the last CDD BOS meeting 10-29-2018 it was voted in to having a service contract with Florida Door Control for Maintenance on the entrance and exit traffic gates. The pedestrian gates will need to be painted because of concrete splashing and concrete sawing dust in areas where concrete repairs and replacement took place by BO's Concrete Company

PLAYGROUND

Nothing to report at this time.

OTHER

Mr, Wellman and Mr. Ed Henson met with professional landscaping companies to develop a scope o0f work for areas such as the circle and both entrances and exit areas at South Patrick & Shearwater Parkway. We will be expecting 2 proposals from 2 different vendors for this work.