08-09-2019

Randy McGrath

Print Friendly, PDF & Email


FACILITY MANAGER REPORT

08-09-2019

Published: August 9, 2019 3:27 pm

Last Modified: August 9, 2019 3:28 pm

Randy McGrath
CLUBHOUSE & GYM

The fitness room will be periodically shut down next week for several days due to the removal of old carpet and installation of new rubber flooring system. We are truly sorry for any inconvenience that this may cause anyone, but this is a necessary and important time frame needed to accomplish what we are trying to achieve. To offer our residents a clean safe environment to exercise in, and to be able to breath normally without smelling the remnants of the old carpets Oder. Thank you everyone for your patience and understanding during this transition period.

POOL & POOL DECK AREA

The pool chemical levels are spot on. We have been experiencing some much needed rainfall lately and I've had to lower the water level several times this week accordingly.

IRRRIGATION

Completed irrigation task week of 8/9/19
Wet check inspection on clock A
Repair main line break behind 658 Monterey. The water pushed a large amount of dirt into the pond that was removed, put back and regraded.
Repair sewer lines at 364 Point Lobos
Moved irrigation valves on to CDD property and reattached the lateral lines at 315 Point Lobos Insight irrigation tested controller C yesterday. All zones had flow. The results can be seen at https://www.easymapmaker.com/map/Montecitocdd.

With all the rain lately, I am making sure that the system is not running. I just saw that there is a flood advisory for Satellite Beach. I don’t think irrigation needs to run for the next few days at least.

The rain sensor on pump 1 seems to have gone bad. I have made Hoover aware. Let us know if there are any questions or concerns.

The pictures below are of the valves that were relocated, the broken main line and the area that was regraded.

Completed irrigation task week of 8/9/19
Wet check inspection on clock A
Repair main line break behind 658 Monterey. The water pushed a large amount of dirt into the pond that was removed, put back and regraded.
Repair sewer lines at 364 Point Lobos
Moved irrigation valves on to CDD property and reattached the lateral lines at 315 Point Lobos
The pictures below are of the valves that were relocated, the broken main line and the area that was regraded.
image.png

LANDSCAPING & LIGHTING

Gault Electric LLC. will come out to replace street light on Redondo. They will also be replacing several power supply boxes along the power supply line that feeds power to the fountains at the entranceway of Shearwater Parkway.

LAKES

These late afternoon and early evening rainfalls have helped tremendously on our water levels of all 6 lakes in Montecito. The Community has a great green appearance lately due to these rains. I give thanks

LAKE FOUNTAINS

Nothing to report at this time.

STREETS & SIDEWALKS

Nothing to report at this time.

GATES & WALLS

Nothing to report at this time.

PLAYGROUND

Nothing to report at this time.

OTHER

Nothing to report at this time.

FILE ATTACHMENTS