CLUBHOUSE & GYM

Painting of the exterior of shed continues the East side of Clubhouse.

POOL & POOL DECK AREA

The removal of plant life along the back side of pool deck took place on Friday 05/24/2019. The beautification & enhancement project is underway and should be completed in the next several weeks once the irrigation system has been reworked and functional. The new cushions for the chase-lounges, and chairs have been ordered by are very own Chairman Larry Bradshaw, A special thanks to Larry for taking the time and effort in picking out these colorful cushions that should last because not only are they colorful but they are also durable as well.

IRRRIGATION

This week we ran our wet check on pump 2 clock d. No real issues with that part besides a few heads and nozzles.
Also we concentrated on Shearwater Dr. Several broken off heads and several clogged nozzles. There is 2 1/2” stub up on the road side of the sidewalk that was broken off, I fixed it. The pots were also redone after the the new plants were installed with micro sprays.
Guysers along Carlsbad were fixed, we fixed the pipes under the porch at 131 redondo and rerouted some broken lateral lines under a bird of paradise plant at 304 point lobos. HOOVER came out and checked out the noise coming from PS#2 and found that one of the motors was bad (NEED of REPLACEMENT). I explained to tje Tech Jason from HOOVER that we have a rewound & rebuilt pump motor in storage ready to install. Due to the fact it was late in the day, Jason told me he would have to schedule this pump motor swap early next week. The PS#2 can operate with the one pump motor until the replacement takes place.

LANDSCAPING & LIGHTING

There is a street light out of order at the East side of the entrance closest to Shearwater Parkway. Gault Electric was notified of this and should be out next week to replace this bulb assembly.

LAKES

Nothing to report at this time.

LAKE FOUNTAINS

Fountain #5 has a bad pump motor and the authorization was given by George Flint (Acting District Property Manager) for replacement. We are at the mercy of Cascade Fountains schedule to come out and complete this scope of work (replacement)

STREETS & SIDEWALKS

There is a street light out of order at the East entrance of Shearwater parkway closest to the roadway.

GATES & WALLS

Nothing to report at this time.

PLAYGROUND

Superior Fence Company came out and removed the pickets from top of fencing around playground and installed rubberized caps in place (TOP) of fenced area for safety reasons.

OTHER

Nothing to report at this time.