Irrigation
Report | Irrigation Notes |
---|---|
12-18-20 | The irrigation controler for PS#1 was not functioning properly and I was not able to remotely control any zones with my cell phone. I reported this to Tuyler Salads of Insite irrigation and he concluded that tjhe temporary repair that was made to this controler antena was indeed failing. The issues must have been repaired because he contacted me and now miraculously I have my remote control abilities back functioning once again Thank you Tyler Salas for the repairs to the irrigation system now allows me to be able to keep water in the South Patrick entrance fountain. Fountain now working. |
10-23-2020 | The mainline break that was behind 710 Montecito Drive has been repaired properly. once the repair had cured 24 hours the system was put back into service. A complete inspection of the repair was made before backfilling the 6" mainline repair. All is well now, PS#2 is back in service and back on the watering schedule. Addressed work orders Installed sprinklers on new plants pump station 1 Started wet check on pump station 1 and found the wiring issues after zone 9 Repaired wiring issues found while wet checking |
10-16-2020 | We have had issues with PS#2, the metal clamps that hold the filters assemblies in tact fell victim to the elements causing the filter covers to separate (FAIL) and cause a leak and the low pressure alarm from massive flow sensors to cause the system to shut down. Hoover came out this week 10-13-20 and make the necessary repairs to the filter manifold. We then had a leak occur in the 6"main line in the proximity behind 710 Ventura Drive. This leak was located and repaired ASAP Unfortunately the cure time on such a mainline break is 24 hours. While the PS#2 pump station was not functioning a water truck was brought in by Paradise Lawn & Irrigation to water all of the areas of concern that PS#2 normally waters. |
10-02-2020 | There are two zones not functioning from the clock. Zone 2 on the East clock and zone 18 on the West clock. Repairs found during clock D wet check addressed work orders |
09-04-2020 | Dear Board Members, Staff has determined that due to an electrical issue, likely a lightning strike, we have a need for new irrigation controllers on Pump Station 1. We currently have no irrigation available until these controllers are replaced. We solicited quotes from both Irrigation Insight ($5,500 for 1 new controller that can replace the three that are down) and one from Paradise (either $10,900 or $12,350). I am attaching both proposals. We have sufficient funds in our FY 20 operating funds to cover the repair costs, as we have only spent through July $10,080 in irrigation repairs out of a budget of $35k. It is our recommendation to immediately proceed with Irrigation Insight due to their expertise on repairs like this, and the considerable cost savings. We would like to authorize the expense, but wanted to see if the Board has any objections to staff proceeding with Irrigation Insight. Although we have been getting rain, we would like to restore service to the SF side ASAP. Let me know if you have any questions, and if we do not receive any objections, we will proceed with authorizing this tomorrow. Thanks and have a good day. Unfortunately I was left out of the loop on the irrigation issues and I have nothing to report This is what I did find out : Randy McGrath (DFS) |
08-21-2020 | Repairs found on clock B wet check Addressed work orders Diagnosed clock D power issue The latest irrigation map can be seen at https://www.easymapmaker.com/map/Montecitocdd. We weren’t able to test clock D this week. That clock had a blown fuse that Paradise is replacing today. The irrigation has been off the last two nights due to rainfall. Let us know if there are any questions or concerns. Rainfall last few days |
07-24-2020 | What check inspection clock B Repairs found on wet check clock B Address work orders Service call for stuck open valve on Monterey |
07-17-2020 | Irrigation wet check on clock A Repairs found on clock A wet check Shut of 314 point lobes that was stuck on |
07-06-2020 | Revamped irrigation around the club house. Revamped irrigation along entryway wall. Addressed work orders Wet checked clock C Repairs found on clock C wet check Repaired down irrigation zone 449 Montecito Drive |
06-29-2020 | Nothing to report at this time. |
05-29-20 | Wet check Clock E Made repairs found on clock E wet check addressed work orders |
05-22-20 | Wet check of clock C Wet check repairs found on clock C Addressed work orders Capped sprinklers were stone was added outside the wall Added sprinklers for better coverage 4 in total Serviced irrigation valve at 314 Point Lobos |
05-08-2020 | The latest irrigation map can be seen at https://www.easymapmaker.com/map/Montecitocdd. There was some concern expressed about ClockD wet check Repairs found on clock D Replace four station decoder on clock A Addressed work ordersthe lake levels. Let us know if we need to shut the irrigation off temporarily. |
04-24-2020 | Wet check on clock B Irrigation repairs found on clock B wet check. Added heads 2 sprinklers for new landscape Addressed work orders. |
04-17-2020 | Finished installing additional rotors around the pond for new landscaping. Reset pump station 3 Clock A wet check clock A wet check repairs addressed work orders |
04-10-2020 | System reset on clock D Repaired damaged irrigation line from pump station 1 repair Addressed all work orders Wet check clock D Pump Station #1 is back up and running. Clock A ran last night. Clock D was reset this morning by Paradise and I can communicate with it once again. It should resume running again as expected tonight. Please let us know if there are any areas that need extra attention and we will do our best to accommodate. Otherwise I will plan on letting things run on their regular schedules. Pump Station #1 had an issue with the manifold failing and separating itself from the pump station.. HOOVER came out and made the necessary repairs last Monday April 6 and 7th. A-OKAY now. |
03-20-20 | Clock C is functioning once again. I have it set up to run extra over the weekend. Worked on clock c 2-wire Replaced solenoid on clock D Repaired lateral line break in common area Made work order repairs in the system |
03-13-2020 | Wet check inspection on clock B clock B repairs found on wet check Troubleshooting wiring issues on clock C I have been communicating with Brandon today. Clock C is currently down with some type of wiring issue. Paradise will be out there to address later this week. |
03-06-2020 | Pump Station #1 was off over the weekend due to a repair. Paradise found a mainline leak that was causing issues on Pump #1. This is good news because it means much less wear and tear on the pump; however, we are still seeing some cycling from the pump when left open (although much less than before). This means there is probably still a small leak somewhere on Pump #1. Wet check inspection clock A Wet check repairs found on Clock a Repaired two main line breaks on pump station one |
02-21-2020 | Wet check inspection on clock C Made repairs on clock C found during wet check Inspected 4 valves that were reported by Insite on clock D |
02-07-2020 | Wet check inspection clock B Wet check repairs on clock B Currently working on clock C 2-wire Addressed work orders |
01-31-2020 | Wet check inspection clock A |
01-24-20 | Made repairs on zones with no flow on clocks A, B, and C. Wet check inspection on Clock E |
01-17-20 | On Wednesday (1-15) Insight Irrigation attempted to run a flow test on clock A. It appears that Hoover was on site and working on the pump stations that day and our test results were invalid. We do know that all zones on Clock A are functioning electrically. Clock C repairs found on wet check Completed revamp for new landscaping around pond on Montecito We will try to get flow results for both clock A and B done next week if possible. Insight will continue to test on Wednesdays and if needed Thursdays. Let us know if there are any questions or concerns. |
01-03-2020 | There was no irrigation report available from Brandon Dietrich of Paradise Lawn & Irrigation as he was in school this week. |
12-13-19 | Installed irrigation on newly planted landscaping Addressed work orders Finished all grounding installation on click D Buried exposed 2 wire on clock E near pump station. Addressed zone 7 and 17 flow problems reported by Tyler |
12-6-19 | This week we tested clock D. Zones 37 (760/762 Ventura), zones 64/65 (122-132 Redondo) and zones 88/89 (pond behind 681 Ventura) failed to show flow. There was new sod put down on zones 29 ,30, 31, 32, 33, 42, 43, 53, 54 on clock D. We will set these zones up for extra watering. Let us know if there are any questions or concerns. Clock D check inspection Clock D repairs Addressed work orders Completed installing 2-wire Clack D |
11-22-2019 | Pump station #2 was changed out with a complete new Pump station by HOOVER on 11/21/2019 and was put into service by Hoover on 11/22/2019 Irrigation items worked on week of 11/22/19 -Irrigation modification along the wall that runs south side of Montecito -Addressed work orders -Main line break clock E -Clock D 2- wire installation, road way crossings. |
11-08-2019 | The latest irrigation test results can be seen at https://www.easymapmaker.com/map/Montecitocdd. This week Insight tested clock E. All zones on clock E are functioning from the timer. |
10-25-2019 | The latest irrigation test results can be seen at https://www.easymapmaker.com/map/Montecitocdd. We tested clock A this week. All zones on clock A are functioning from the timer once again. Addressed work orders and repairs Clock E is having communication issues and Insight will be there today to inspect the clock. I will update everyone once inspection is complete. Let us know if there are any questions or concerns. Clock E is having communication issues and Insight will be there today to inspect the clock. I will update everyone once inspection is complete. Let us know if there are any questions or concerns. Clock E is having communication issues and Insight will be there today to inspect the clock. I will update everyone once inspection is complete. Let us know if there are any questions or concerns. |
10-18-2019 | Addressed work orders and repairs Finished wet check on A and made repairs |
10-11-2019 | Irrigation work performed week of 10/11/19 Addressed work orders and repairs Replaced broken spray heads at the following addresses 708 Monterey, 728 Monterey, 658 Monterey, 726 Vetura, 719 Vetura, 723 Vetura, 103 Redondo. 128 Clemente, 136 Clemente |
10-04-2019 | Irrigation work performed week of 10/4/19 |
09-27-2019 | Irrigation work performed week of 9/27/19 |
09-20-2019 | Irrigation work performed week of 9/20/19 |
09-13-2019 | Irrigation work completed from 9/5/19 -9/13/19 |
09-06-2019 | Unable to receive any report from Paradise Lawn & Irrigation at this time. In a holding pattern, waiting on report. When I receive it, I will send out an addendum report. |
08-23-2019 | Completed irrigation inspection on clock C and all repairs. Trouble shooting of clock D and E Replaced 2 wire module on clock E under factory warranty. Repaired wire issues on clock D and E Clock E zones 1-13, 25, 26 are not operational (we are find many different types of wire) Clock D is continuing to have wiring malfunctions has been on and off throughout the week currently not operational. Manual watering around the club house and pool deck. Paradise will have are team out Monday to finish wiring repairs and start new wire installation on 9/3/19 Thank you |
08-16-2019 | Montecito 8/16/19 Irrigation inspection clock B and repairsMontecito 8/16/19 Irrigation inspection clock B and repairs Tyler Salas All, This week Insight went back and tested all of the failed zones on clocks A-C and some of the zones with flow “concerns.” Here are the results https://www.easymapmaker.com/map/Montecitocdd. Zone 54 on clock B, which waters the roundabout in front of the clubhouse, is the only zone on clocks A through C that does not operate from the timer. All other zones are working. We were not able to test clocks D or E this week since both clocks are shorted. I know Paradise Lawns was on site yesterday searching for the short on clock E. Let us know if there are any questions or concerns. Thank you for updating the map. I noticed that zone 54 shows as no flow I believe this is because well station 2 provides the water for this zone. Next time you run a test will you try zone 54 on clock B with well station 2. We are working to resolve the problems on clock D and E rain has been hindering us this Week while working on electrical issues I will notify everyone when they are back up and running. I tried testing zone 54 and watching for flow on Pump station 2. You are correct. It is getting water from pump station 2 somehow. Very strange because it did not used to be that way. Perform Visit 2 of Preventative Maintenance per Contract. Serviced all hydraulic pilot components, flushed |
08-09-2019 | Completed irrigation task week of 8/9/19 With all the rain lately, I am making sure that the system is not running. I just saw that there is a flood advisory for Satellite Beach. I don’t think irrigation needs to run for the next few days at least. The rain sensor on pump 1 seems to have gone bad. I have made Hoover aware. Let us know if there are any questions or concerns. The pictures below are of the valves that were relocated, the broken main line and the area that was regraded. Completed irrigation task week of 8/9/19 |
Addendum for Irrigation 08-02-2019 from Paridise Lawn & Irrigation | Completed Work orders Worked on wiring faults on clock B and completed repairs on zones 7,8,9,30,and 40. Rerouted the Mail line for new pool at 315 point lobos. Inspection on clock B. |
08-02-2019 | Insight tested controller B this week. The following zones failed: Zone 4 (727 Palos Verde) Brandon Dietrich informed me that they are having some trees/bushes removed so they can access the valve for zone 4. Zone 54 (roundabout in front of clubhouse) Zone 57 (269 Montecito). Zones 16 (315 Point lobos) and 19 (rotors on pond) on clock B are having work done on the pipes so I labeled them as “pools” for now, meaning those zones are down temporarily for repairs. All, Pump station #3 is currently in rain shutdown. The rain sensor on Pump #1 did not put the system in rain shutdown this morning for some reason. Just be aware. I am going to request that Hoover take a look at the rain sensor on that pump. |
Addendum 07-26-2019 | Work order repairs 761 Ventura – replaced 1 - 6” spray and 1 nozzle Zone 1 – replaced 4 / 12” spray heads |
07-26-2019 | All, A couple things have happened and I want to make sure everyone is in the loop. Paradise found the valve behind 717-731 Ventura throttled down. That building is receiving water again. Paradise has been working on rerouting/repairing pipes for pool installs. Pump #1 did not operate last night because the butterfly valve was left closed overnight. Once the butterfly valve was reopened, one of the places where the pipe was rerouted/repaired came apart. Insight has been testing timer A today. We will have the results posted on the map by tomorrow. Will email everyone with the updated results. Gator Tyler Salas – Irrigation Manager Hoover came out and installed a new air relief valve at PS#3 on July 25, 2019 Tech name was Jason He arrived at 5:30 pm. and departed at 6:00 pm. |
07-19-2019 | Monday 7/15/19- system inspection on clock A, Cleaned out 2 stuck valves on clock D zones 54 and 34, addressed work orders that have been called in. Thursday 7/19/19- Located stuck open vale on clock D, replace valve zone #1 |
07-08-2019 | Monday July 1st Tuesday July 2nd Wednesday July 3rd |
06-21-2019 | June 18 Repaired main line break behind 696. Stubbed up and capped mainline between 668,658, and 648. The water is OFF at this clock, waiting on contractor to finish excavation work. June 19 Rewired zone 4 valve to Decoder. Multiple zones were stuck on due to dirt/rocks in the system caused from a mainline break. Disassembled, cleaned and rebuild valves. |
06-14-2019 | Montecito, controller B The mainline break on Monterey in the back yard has been repaired and paid for by party the did the damage.. |
06-07-2019 | Nothing to report at this time. No report given by Paradise Lawn & Irrigation this week. Irrigation Manager is not in the office today.. Sorry for the inconvenience, Paradise will not be able to send this weeks report today.. Please feel free to contact me if you have any questions.. |
05-31-2019 | This week we did A wet check on clock d which is the new construction area. A few broken heads and clogged nozzles. |
05-24-2019 | This week we ran our wet check on pump 2 clock d. No real issues with that part besides a few heads and nozzles. |
05-20-2019 Addendum Irrigation Report | Addendum irrigation report from 05/17/2019: This week we did our weekly wet checks and we took care of clock C which is all the homes on point Lobos drive and Monterey Drive.. I was in contact with Tyler from Insight and he informed me of the few zones that had high flow. On the end of the perimeter wall on the outside on shearwater zone one clock D was a high flow zone and I fixed a gushing head and repaired and exposed bubbler line that had been cut. I was in touch with the technician from Brevard lawns who is installing the irrigation on the new homes on Redondo Drive . Installed an electric valve on the last townhome and I was able to put it on the timer activating it automatically. South Patrick entrance north end I replaced a broken head by the wall and an exposed lateral line that have been broken along the ditch line flooding into the ditch. The walkway to the park from Monterey Drive I fixed a broken lateral line under the mulch that has been flooding the sidewalk. I also fixed a tree bubbler that had been cut along the sidewalk. On Montecito drive next to the pump station on the city strip in between the sidewalk and the street had a broken lateral line due to pool construction of the house on the corner. That was repaired and several heads were cleaned out. Approximately 10 work orders were closed out ranging from a leaky head, to poor coverage, to I don’t know if my yard is on the timer. I am here now (Friday) looking into a few things from Tyler and checking a few work orders. Report written by Mike Billquist (tech from Paradise Lawns & Irrigation). Thanks Mike |
05-17-2019 | I wanted to touch base with you about the irrigation work this week. We are doing wet checks every week so we have been servicing one clock per week. Last week was clock A and this week we did clock B. I have been trying to focus on the larger issues like zones not activating or high flow zones. Tyler has been very helpful in finding problem areas. Working off his report I was able to locate three zones that were not active due to a bad decoder. 696 and 686 palos verde and the common area behind them both had not been getting any water and are now active. We also took care of some work orders and requests from William. The gushers in the city strip on Carlsbad were also replaced. |
04-19-2019 | : Paradise Lawns & irrigation has been diligently working on trouble-shooting irrigation issues at 404 Point Lobos Drive, 656 Palos Verde Drive, and 649 Monterey Drive (NOT WATERING). They are repairing these and many other irrigation issues on Carlsbad Drive too. The Pump Station #1 concrete reinforcement project has been completed. |
04-12-2019 | : The concrete reinforcement project was formed up, poured, and finished this week on Pump Station #1. On 4/12/19 at 9:00 pm. there was a major vertical line break reported in the SF homes section at 678 Monterey Drive (rear) of property control box area. This repair was made by Paradise Lawn & Irrigation company promptly and professionally. The status of the geysers on Carlsbad Drive is ongoing, I received no report? |
04-06-2019 | : There is a major leak was reported at the rear property of 686 Palos Verde Drive (Robert Schweiger residence). I shut the power supply was shut off due to this after-hours emergency, I contacted Tyler Salas of Insight’s Irrigation Manager/ monitor to make him aware of the situation and status of PS#1. There have been several geysers reported on Carlsbad Drive and Paradise Lawn & Irrigation Co. have been diligently locating and repairing issues of stuck valves on the 700 block of Ventura Drive. I believe that in due time these geysers will be repaired ASAP. I’m not certain who put a lock assembly on PS#1 main water control valve, but this info should have been communicated with Ed Henson, William V., Jason Showe or myself Randy McGrath. |
03-30-2019 | : All, |
03-23-2019 | : The concrete jacking or pumping for PS #1 will begin soon. We continue to wait for HOOVER to address the issue of flange leaking inside of PS#2 pump housing. PS#3 has added a new watering ZONE in the common areas behind the first housing unit on Carlsbad Drive. This ZONE was added to the watering clock by Brevard Lawn & Irrigation Company; I will be meeting with Tyler Salas on Monday March 23, 2019 to determine exactly what area this ZONE covers and label it in the system. I will be meeting with Superior Fence Company on April 2,2019 to get a bid for putting a fence around PS#3 as needed. I will order the correct signage for this PS#3 gated area. |
03-16-2019 | : The PS #2 was turned off because of a mainline break at the North east corner pond #6 in the undeveloped area Clemente Drive / towards Simeon Drive. This repair was made by Brightview and PS #2 was turned back on after the correct curing time of the repair. I was adjusting the timer for fountain #4 lighting because of time change, when I noticed water coming out of the PS #2 housing. Evidently parts were ordered by HOOVER pump company, and we await the arrival of the parts. A plastic covering was installed over the electrical components by Brightview. Although PS #2 has this leak issue, this PS #2 can continue to operate until the repair takes place. |
03-08-2019 | : Pump station #3 ZONE #24 clock E not communicating with Insight programing. After investigating this issue, it was indicated to me by Tyler Salas that a control box on the North side of Redondo Drive, approximately from 104 Redondo Drive all the way to Carlsbad Drive were affected. The control valve had been screwed down for reasons unknown. Once the valve was opened and ZONE E was programed to the watering cycle, all is well now ZONE 24 is now functioning fine. |
02-15-2019 | : The only thing to report is the main line was relocated at the Wilson residence rear of property 689 Monterey to be able to excavate for swimming pool installation. The irrigation system for the SFH was (SHUT-OFF) during this procedure / curing of pipe as well. |
02-09-2019 | Nothing to report at this time. |
02-08-2019 | : Clock A Clock C Clock D |
02-01-2019 | We inspected the controllers and pumps New wire was ran from the decoder to the solenoid at zone #40 on Clock D New wire and a decoder has to be installed on zone#3 on clock C, until that is completed we installed a battery pack on that zone A broken 6” popup was replaced in the CDD strip in front of 677 Ventura |
01-25-2019 | .Irrigation pumps: Montecito – January 25, 2019 Controller A The FLO GUARD app for PS#3 was installed on the CDD office computer, soon I will have the PS#1 app installed to the office computer. Too. I just have to reach out to HOOVER and get the necessary accessibility information. PS #2 will not have this capacity until the PS#2 gets the new pump station in 2020. |
01-18-2019 | Nothing to report at this time. |
01-04-2019 | We began our monthly irrigation inspection and repairs on Wed. As of yesterday the technicians completed Controllers A and B on PS#1. All of the controllers have been reprogrammed and a new schedule has been sent to the CDD and HOA. |
12-21-2018 | Irrigation pumps: SFH Pump station #1 had a complete (NEW) irrigation equipment changed out. There is an issue of erosion in this area of the equipment platform. GMS has several bids in place to reinforce these equipment platforms with a process of concrete jacking. This is where hydraulic cement is formed up and pumped in these areas to shore up the platforms. |
12-21-2018 | Nothing to report at this time. |
12-14-2018 | This week we completed the minor irrigation repairs per pre approval from our last inspection. The mainline, 2 wire and valves were moved in the SFH section ahead of the swimming pool installation. |
11-30-2018 | The new suction line was installed by Hoover in Pump Station #2. Both P# #2 and #3 were out fitted with back flush system in order to backwash / clean intake screen when needed.. |
11-09-2018 | · We completed all of the approved repairs from Septembers irrigation inspect · The October irrigation inspection was completed and we will be sending that report over soon · We have received a pre-approval to make CDD repairs while we are onsite completing our inspection. · We repaired a mainline outside of the wall along Shearwater. · We installed 2 spigots were installed along Shearwater. · Both pump stations and all 4 controllers were inspected. |
10-19-2018 | On Monday we inspected both pump stations and all 4 controllers. Controller C had an alarm on every zone which indicated a 2 wire splice out in the field. We located the wire splice which was over 1,100ft away from the controller at a depth of 5’ deep. It was a small nick in one of the strands that had corrosion. A new section of 2 wire was installed with a splice box. We have started making the approved irrigation repairs from our September irrigation inspection and will be working on our October irrigation inspection. |
10-12-2018 | This week all of the controllers were checked for alarms. PS#1 on Controller B had a 2 station decoder alarm for zones 22-23 and Controller C had a 2 station decoder alarm for zones 28-29. We had a mainline break behind 664 Mission Bay. The irrigation for PS#1 was turned off to allow the line to drain. This repair is being completed today. A ball valve was installed, so the water to PS#1 will be turned back on today. We submitted our irrigation inspection report to GMS, Jason Showe sent over the approval, a PO will be issued for the parts and the repairs will be scheduled. |
10-05-2018 | We installed the approved new decoder for zones 22-23 on PS#2. No other alarms were found on the controller. On PS#1 we found no alarms on controller A, on Controller B we found a bad 2 station decoder (zones 22-23). On Controller C we found a bad 2 station decoder (zones 28-29). The proposal for replacement of these decoders has been approved and are scheduled for installation next week. On PS#1 we found no alarms on controller A, on Controller B we found a bad 2 station decoder (zones 22-23). On Controller C we found a bad 2 station decoder (zones 28-29). The proposal for replacement of these decoders has been approved and are scheduled for installation next week. On PS#1 we found no alarms on controller A, on Controller B we found a bad 2 station decoder (zones 22-23). On Controller C we found a bad 2 station decoder (zones 28-29). The proposal for replacement of these decoders has been approved and are scheduled for installation next week. We repaired a broken lateral line and 12” popup on the exit side of the Shearwater entrance. We repaired a broken lateral line and 12” popup on the exit side of the Shearwater entrance. We repaired a broken lateral line and 12” popup on the exit side of the Shearwater entrance. |
09-28-2018 | The mainline reroute has been completed and normal Irrigation schedule will resume this evening. A PO for approved decoder for zones 22-23 will be issued on Monday and the decoder will be installed on Monday. |
09-21-2018 | All of the repairs from the August irrigation inspection have been complete. 2 approved decoders have been installed. The September irrigation inspection has been completed and will be sent over to Jason Showe for approval once the paperwork has been completed. All controllers and pump stations were inspected on Monday and no other alarms were found. |
09-14-2018 | 3/4 of the approved August repairs have been completed. The rest will be completed next week. We found (2) bad decoders in the SFH and those will be replaced next week. No other alarms on the controllers. |
09-07-2018 | PS#2 HOOVER brought in their diver and reported that the 6" suction line will need to be replaced ASAP because of voids / breaks in this line.. It seems that the intake suction stub has failed because it is to close to the bottom of the pond floor causing low pressure to irrigate efficiently. HOOVERS recommendation is a total replacement of the intake suction line and the automatic flush feature will also need to be replaced as well. we are waiting on a proposal price on what this will cost. This explains why PS#2 has been not being able to function properly, due to low pressure. |
08-31-2018 | There was no report turned in to us about the irrigation systems. This is unusual and unexpected because of all of the issues that we've been experiencing lately. We await the findings and report from HOOVER on what was found after their inspection of the PS #2 intakes situation? This week we finished our approved July irrigation repairs and our August irrigation inspection. Once the paperwork is completed I’ll be sending the report To the CDD for approval. We replace 2 decoders on PS#1 on Clock C. A mower cut the exposed 2 wire at the end of Clemente and Alex came out and repaired. Both pump stations and filter rings were inspected and found to be in working order. |
08-24-2018 | We checked both pump stations and all 4 controllers for alarms. Both pump stations were operational with no alarms. Pump station #2 is still only irrigating 1 zone at a time, so luckily Mother Nature is helping us. Hopefully the Hoover diver will be out to inspect and clean the Suction line intake and we will be back to regular capacity. We found a couple decoder alarms of PS#1 controller C, these zones were on the East side of Monterey drive. We replaced a 2 station decoder and a 4 station decoder. We have almost completed our August irrigation inspection and July repairs. Once the inspection is complete, I’ll send over the inspection report to the CDD for approval of repairs. |
08-17-2018 | We inspected both pump stations and all 4 controllers and found no alarms. PS#1- We repaired the approved mainline leak between zones 4 and 5 on Controller C and reconstructed the 4 valves. After the repair had cured and the mainline was pressurized, the next weak spot in the mainline blew. The line was opened up and drained overnight, we returned on Friday to repair and irrigation for PS#1 is back online. We will be completing the approved July irrigation repairs and completing our August irrigation inspection next week |
08-10-2018 | Pump station #2 was found tripped and was reset on Monday. All zones are operational, however we are having pressure issues while the system is running through the normal programming. The CDD has approved a proposal for Hoover to inspect and clean the intake screen which is out in the pond. In an effort to insure each zone is receiving adequate pressure we have reprogrammed the controller and each zone is running twice per week, 7 days per week. |
08-03-2018 | .This week we inspected both pump stations and all 4 controllers and no alarms were found. Our July irrigation inspection was approved. The approval was sent to the office so a PO can be issued for the materials. Our July irrigation inspection was approved. The approval was sent to the office so a PO can be issued for the materials. |
07-27-2018 | Irrigation We inspected both pump stations and all for controllers and found no alarms. |
07-20-2018 | This week both pump stations and all 4 controllers were inspected and no alarms were found. The filter rings were inspected and found to be in fair condition. We are continuing to work on our July inspection. Jason Pilon |
07-13-2018 | We inspected both pump stations and the 4 controllers and found no alarms. The approved valve replacement for the units 129-139 Montecito drive was completed. We have started our July irrigation inspection. On July 11,2018 : A technician onsite who will be treating the torpedo grass in plant material and also treating the Hawthorne for Weevils. |
07-06-2018 | Last week we replaced bad solenoids at 628, 638, 689 and 769 all on Monterey drive. A 1 station decoder was replaced at 434 Point Lobos Dr A 2 station decoder was replaced at 128 Redondo Dr We had an alarm on Controller D for zones 52, 53, 54 and 55. We discovered a corroded wire at the 4 station decoder. We replaced 3 heads for along Shearwater for free due to lack of authorization to preform work, thus we cannot bill for the work. We pulled a tech from another property to come run the irrigation for the company working on the fountain pumps- for free I sent a copy of our irrigation maps to the company hired by the CDD to assess the irrigation system.This week we inspected the controllers/ pumps and found no alarms. A proposal to replace a 2” valve which operates a zone for 139 Montecito was approved. This valve was continuing to partially close which reduced the pressure for the entire 6 plex. |
06-15-2018 | Irrigation pumps: All of the approved irrigation repairs from our May Irrigation inspection were completed. We inspected by pump stations and filter rings and found everything in good order. A 2" stuck valve was replaced at 439 Montecito. We have completed our June Irrigation inspection, which will be sent over when the paperwork is completed. |
06-08-2018 | Irrigation pumps: This week we checked all 4 controllers and found no alarms. |
06-01-2018 | Irrigation Pumps: The weak theinigatlon controllers at both pump stations have remained off. The repairs listed on our May irrigation inspection were approved. Alex has started making those repairs and they will be completed by next week. |
05-25-2018 | Irrigation Pumps: We completed our monthly Irrigetion inspection. Alex is completing the paperwork this weekend and I' ll be sending the report over this weekend. We have been primarily leaving the irrilation off due to all of the rain. Hoover came out and attempted to repair the leaking filter at ml, however due to the location of the leak and the amount of rust on the bolts, he has to return with more parts. There is a chance that the bottom section of the filter housing has cracked and would need to be replaced. The only way to know for certain will be when he takes the whole thing apart. Due to all the fresh water fimng the ponds, the pond levels are looking much better and the rain also helps the water quality we are irrigating with. |
05-04-2018 | Irrigation pumps: Both pump stations and all 4 controllers were inspected. We replaced the 28 valve on Clock A Zone 24 The decoders for zones l'-J.8,36-31, 46)41.48149 were replaced |
04-27-2018 | Irrigation pumps: We inspected both pump stations and filter rings. We found no pump alarms and the filter rings were in decent shape. |
04-20-2018 | Irrigation pumps~ This week both pump stations were inspected on Monday and no alarms ware found on alarm controller. |
04-13-2018 | Irrigation pumps: We Inspected both pump stations and all 4 controllers and found no alarms. Alex has completed his Inspection on PS#2 and once the paperwork ls completed it will be sent to the COO and HQA for approval. Alex. Christian and Brad have been working on the irrigation upgrades for the new enhancement projects at both entrances and monument signs. |
04-06-2018 | Pump station #2 is back to full operation and is on normal watering schedule. We inspected all 4 controllers at Pump station #1 and #2 and we found no alarms at any of the controllers this week. The filter rings at both pump stations were inspected and are in good condition. |
03-24-2018 | Irrigation pumps: SFH/TH, there have been so many variables pertaining to both irrigation systems, from wire breaks and to underground main line breaks in the installation process of two swimming pools in adjacent homes. The TH irrigation system has been interrupted recently from equipment failure (BAD #1 Motor) electrical components heating up and shorting out internally. These are unforeseen issues even though they are unfortunate circumstances are frustrations are many in maintaining the irrigation system. We have a maintenance agreement in place with Hoover Pumps as we find ourselves at their mercy and maintenance schedule. Brightview only handles the smaller type issues like sprinkler heads and wire issues and irrigation line repairs. The equipment at the pump stations are Hoovers responsibilities and depending on how major the repairs become determines if Brightview is able to make the repairs or not. Thanks goes out to the community for their patience and understanding in this manner. |
03-02-2018 | Irrigation Pumps: The sFH irrigation system is out of order until Tuesday March 6, 2018 due to a mainline break caused by the pool installation crew ruptured this irrigation line while excavating the second of two pool being installed at 738 and 728 Monterey Drive rear of property closest to pond #2. The actual repair will take place on Monday March 5, 2018, But there is a 24 hour cure time on the repair before re energizing the irrigation system. We are sorry for the inconvenience this may be causing the SFH residents. The TH irrigation system is operating fine at this time. |
01-12-2018 | The SFH & TH irrigation repairs from December were authorized and completed this week, and the January inspections were started also. The filters and pump stations 1 & 1. were also inspected. they all checked out fine and are fully functional at this time. |
01-05-2018 | The SFH and TH pump stations were turned OFF yesterday 1/04/2018 because of the freeze factor (WEATHER CONDITIONS) below 32 degrees. Both systems were put back in operation this morning 1/05/2018 and both systems are functioning fine at this time, nothing to report. |