4 results returned.

CIP Category: Security

Project Project Status When CIP Funding Estimated Costs Final Costs
Update Fire Alarm System Complete 2nd Qtr 2020 2019/2020 $16,419 $16,419
Update Clubhouse Access System Complete 2nd Qtr 2020 2019/2020 $8,503 $8,503
Add Security Fence Around Pump Station #3 Complete 3rd Qtr 2019, 2019 2018/2019 $2,499 $2,500
Replace Security Camera System Complete 3rd Qtr 2018 2017/2018 $14,000 $8,795