District Capital Improvement Projects

The CDD Board of Supervisors authorizes funds from time-to-time to be spent for improvements to the District out of the Capital Improvement Project Reserves. To see possible future projects and proposed time-frame, visit the 2018-2023 Capital Improvement Project Plan. Previous items that were listed as Capital Improvement Projects, such as: Palm Tree Trimming, Oak Tree Trimming, Sidewalk Power-washing, and Street Light LED conversions, are now considered annual maintenance items and will be cared from under standard Operations and Maintenance budgetary items.

Hyperlinks to individual project detail and filters are available in the tables below by clicking on any hyperlinked item, such as the Project Name, a Category, a Status or Timetable (i.e. When). You can also view all projects in calendar year 2019 or 2020.

Capital Improvement Projects Not Yet Complete

The following list of projects were approved by the CDD Board of Supervisors but have not yet been completed but are either already started, scheduled or will be scheduled this year.

Total Estimated Costs to Date $54,538.

The following list of projects were completed and funded with fiscal year 2019-2020 Capital Improvement Project funds.

23 Projects Category When Final Costs
Add 10 New Benches throughout the Community Landscaping, Perimeter Wall, Right of Ways 3rd Qtr 2020 $15,236
Clean Up Exterior Wall Bench Areas and add Red Crimson Rock Landscaping, Perimeter Wall 2nd Qtr 2020 $3,380
Install 2 New Stops (4 Signs) and Paint Crosswalk Right of Ways 4th Qtr 2019 $3,000
Install Bike Racks Outside Pool Area, Playground and Fitness Center Clubhouse, Playground, Pool / Pool Deck 3rd Qtr 2019, 4th Qtr 2019 $4,541
Interior Former Pergola Cleanup Landscaping 1st Qtr 2020 $1,035
Lake Catalina Erosion Control Landscaping 2nd Qtr 2020 $2,735
Paint Inside of Perimeter Walls (SFH Section) Perimeter Wall 3rd Qtr 2020 $10,950
Paint interior side of perimeter wall in townhome section Perimeter Wall 1st Qtr 2020 $5,495
Paint pedestrian gates and monument trim Perimeter Wall 1st Qtr 2020 $1,414
Painting Inside of Perimeter Walls (North Perimeter Wall) Perimeter Wall 3rd Qtr 2020 $2,035
Removal of Shrubbery/Plant Material along inside of Shearwater Perimeter Wall Landscaping, Perimeter Wall 4th Qtr 2019 $12,096
Remove Hedges Around Lake Coquina Landscaping 1st Qtr 2020 $8,879
Remove Pergolas Perimeter Wall 1st Qtr 2020 $9,335
Repair Entrance Fountains (Continuance from Previous Year) Perimeter Wall 1st Qtr 2019, 2nd Qtr 2019, 4th Qtr 2018 $3,647
Replace 2 Sidewalks Right of Ways 2nd Qtr 2020 $2,447
Replace Clock D Wiring for all Clock D Zones Irrigation 3rd Qtr 2019, 4th Qtr 2019 $26,400
Replace Pump Station #2 Irrigation 4th Qtr 2019, 2019 $58,239
Resurface Pool Marcite, Replace Tiles and add LED lights Pool / Pool Deck 1st Qtr 2020 $37,757
Shed Landscaping Landscaping 4th Qtr 2019 $2,165
Sod Replacement, Viburnums, Mulch, etc Landscaping 1st Qtr 2020 $5,951
Stain exterior clubhouse ceiling areas and clubhouse exterior touchups Clubhouse 1st Qtr 2020, 4th Qtr 2019 $3,850
Update Clubhouse Access System Clubhouse, Security 2nd Qtr 2020 $8,503
Updated Clubhouse Entrance Landscaping Landscaping 2nd Qtr 2020, 3rd Qtr 2020 $9,489
Total Final Costs to Date $238,579.

The following list of projects were completed and funded with fiscal year 2018-2019 Capital Improvement Project funds.

Total Final Costs to Date $193,353.

The following list of projects were completed and funded with fiscal year 2017-2018 Capital Improvement Project funds.

Total Final Cost $61,127.